How Long Does It Take To Renovate A Bathroom?

The bathroom offers a momentary oasis of solitude and is the perfect place to unwind from daily stresses. It is more than just a maintenance room where our day begins. Therefore it is essential to be focused when you are thinking of renovating a bathroom.

Estimating the duration of a bathroom renovation can take time and effort. Once you think you have the schedule in place; however, it changes. Worker illness, supply delays, payment errors, or unanticipated structural issues can all happen. Given the variety of services that bathrooms require, it can take time to estimate a precise completion date.

 

We’ve listed a few factors to consider below for your renovation timeline.

 

Why Renovation:

Remodelling your bathroom is one of the best ways to revitalise your home. It doesn’t always mean tearing your bathroom apart to remodel; just replacing your vanity or shower can make all the difference. You can also start from scratch if you want to remove everything. It all depends on your goal and, more importantly, your budget. There are many reasons for bathroom renovations.

⦿ Make more room in your storage

⦿ Solves any existing issues

⦿ Makes your bathroom look more modern

⦿ Boosts the resale value of your home

⦿ Adds functionality to your bathroom

 

Duration For Remodeling A Bathroom?

In an ideal scenario a bathroom can be finished within 15 – 25 days. Renovation projects for bathrooms rarely go as planned, despite the best planning. Understanding the determinant is necessary for precise factors, though.

 

  •  The Project’s Scope:

Are you putting in your own time? One can expect a project to take up to a year or longer to complete if one handles all the work.

 

  • How Do You Plan To Complete The Task?

Do you want the work done by a general remodelling company or independent subcontractors? Your decision will solely be based on your budget and the urgency of the project. If you want the project finished quickly, it’s best to hire a reputable general renovation contractor.

 

  • Material Accessibility:

The availability of materials can significantly impact the project’s completion time. Accessible locally, all the materials like shower systems, premium faucets, bathtub etc wouldn’t affect the lifespan of your project. For a smooth project progression, always work on a workable project plan and gather the materials in advance.

 

Prepare For The Unexpected:

Here, we have listed some points that will help you regarding the time when renovating your home.

 

Demolition (2-3days)

Removing waste from a bathroom on the second floor is arduous work that might take longer.

 

Tactical Carpenter (1-2 days)

Optional: If the underlying structure is in good shape, you might not require a carpenter.

 

Plumbing Rough-In (2-3 days)

If you are moving amenities like the bathtub and toilet, allow at least two days.

 

Electrical Rough-In (1-2 days)

It would be rare for this to take longer than a day because a great professional electrician can work quickly. Rough-in refers to running electrical lines but does not include making the final connections.

 

First Examination (1 day)

The initial inspection that must be completed before the drywall work is finished moves quickly and shouldn’t take more than one day. However, this could delay the remodel by a week or two due to difficulty in scheduling inspectors.

 

Insulation (4-5 days)

It is essential to shield a bathroom immediately because there are typically only one or two walls involved. Remember that this step will take longer if an insulation inspection is necessary for your area.

 

Complete Drywall (2-3 days)

Applying joint compound, letting it dry, sanding, and occasionally repeating these steps is finished.

 

Paint (1-2 day)

It is relatively quick and easy to paint a bathroom while still unfinished. No masking is needed, excluding the ceiling.

 

Final assessment (1 day)

The final inspection takes at most 20 minutes.  The inspector’s appointment, however, might cause a delay in your work.

 

Two Ways to Speed Up a Bathroom Renovation:

You cannot control the uncontrollable as the client for the bathroom remodel. But there are things you can change on your end. If you’ve completed all of these steps. The contractor will once again be in control of the timeline for the bathroom renovation:

 

  • Pay all invoices promptly or on time:

Contractors rely on your expenses because they must reimburse other parties.

 

  • Be accessible:

Calls, texts, and emails from the contractor must be returned as soon as possible. The entire schedule will be pushed back by one day if you wait an extra day to contact the contractor.

 

Let’s Get Started!

Are you contemplating a bathroom remodel project but need help knowing where or how to start? We hope the factors that we listed above will help you construct a modern bathroom for your space. Also, you can visit our website if you are looking for online products. Fima the leading Italian sanitary ware brand has a wide array of stylish & sleek sanitary ware products that will make your lavatory look opulent.

 

May 19, 2024, 3:04 am
Enquire Now